CURRENT
PROJECT
Funding to construct the park is a shared partnership between the City of Langford and the Wheelhouse Cycling Society. Building partners include Workhorse Trail Design, JD Parks, and Velosolutions.
With a proposed $1.4 Million budget, the Society has agreed to set a community fundraising target of $100,000 in contribution to this goal.
OVERALL PARK BUDGET
Bridges and Culverts - $120,000.00
Parking Lots - $80,000.00
New Trail - $90,000.00
Jump Park - $125,000.00
Pump track - $265,000.00
Bike Skills - $65,000.00
Clubhouse - $300,000.00
Sewer Connection - $50,000.00
Consultants - $40,000.00
Miscellaneous - $75,000.00
Total - $1,210,000.00
Contingency - $181,500.00
OVERALL TOTAL - $1,391,500.00
CONTRIBUTIONS AND FUNDRAISING
Volunteer hours ($20/hr) - $48,000.00
Corporate Sponsorship - $50,000
Crowd Funding - $100,000
In-kind Sponsor of Materials - $100,000
Event Fundraising - $20,000
TOTAL = $318,000